Client
LTT
Location
Zawia street post office,
information
- Supply and installation 350kva power generator in main location (zawia street post office )
- Supply and installation 7 power generators (20-45-60 kva) in central rejoin.
- Project of upgrading the electrical system (generators-electrical panels –cables) rating 35-45-60-165-350-500 kva , in data center alamros (synchronization system),km4 main station (synchronization system), abuoseta LTT the headquarter) ,VSAT building abouseta,Tripoli university ,sede slim location ,geryan main branch
- Project upgrading the main electrical power room (supply and installation 2 of 750KVA) (synchronization system) In the the headquarter.
No comment